|
QUIKWALL®
Surface Bonding Cement (SBC) now makes most block construction
possible without using mortar; it's literally a "stack and stucco"
project. A single coat on dry-stacked block gives a handsome stucco
finish and provides greater flexural and impact strength than mortar
with less approximately 50 square feet to a 1/8" thickness. In
planning your project, note that actual rather than normal block
size is used since joints are not buttered.
Block
Walls
The same basic
techniques of wall construction are used no matter what your project
happens to be.

- QUIKRETE®
Surface Bonding Cement
- QUIKRETE®
Concrete Acrylic Fortifier
- QUIKRETE®
Sand Mix or QUIKRETE® All-Purpose Sand (if needed) QUIKRETE®
Concrete Repair Caulk
- Mason's
line
- Level
concrete or joint trowels
- Chalk line
- Mason's
hammer
- Brick
set
- Straight-edge
- Metal tie
bars
- Metal lathe
strips
 Construction
1.
Construct the footer for the wall.

2. To
ensure square, accurate corners and straight walls, dry-lay the
corner leads and first course and chalk mark the block positions on
the footer. Use a level and mason's line for accuracy.
3. Remove
the blocks and lay 1/8" bed of prepared QUIKWALL® SBC on the footer.
This bed of QUICKWALL® SBC helps in leveling the first course if
there are slight irregularities in the slab of footer. Relay the
bottom course checking alignment and level every 3 to 4
blocks.
 
4. For
projects with wall openings or intersecting walls (other than at
corners), refer to steps 6 and 7. Otherwise, dry-stack the remaining
block in a running bind pattern to the desired height. If necessary,
shim with QUIKRETE® All-Purpose Sand or Sand Mix.

5. Wet
down the wall and apply 1/8" QUICKWALL® SBC coat to both the sides
and exposed ends of wall using a finishing trowel with an upward
motion. If you must stop work, stop the QUIKWALL® SBC application on
a block, not a joint between blocks.
 
6. Stack
and bond the main and bearing wall intersection together in 4- to 6-
course intervals. After the main wall has been stacked and coated no
higher that 6 courses , begin constructing the intersecting wall. If
too should be placed and leveled in an 1/8" bed of QUIKWALLâ SBC.
Embed metal ties every 4 to 6 courses as shown. Stuffing the bottom
of the block cell opening with paper will allow you to fill it with
paper will allow you to fill it with mortar to hold the tie.
Continue to build the intersection in intervals to the full height
of the wall.

7. To
construct window or door openings, dry-stack the block no more than
2 or 3 courses higher that the bottom of the opening before framing
out the opening to exact dimensions. The wall is then built up
around the frame. Precast lintels make finishing the top of doors
and windows easy. Because precast lintels are nonporous, the
QUICKWALL® Surface Bonding Cement applied over the lintel must be
fortified with QUIKRETE® Concrete Acrylic Fortifier. Simply lay the
lintel in place and coat it with fortified QUIKWALL® SBC
mix.

8.
Vertical control joints are needed to handle stresses and prevent
cracking of the block or QUICKWALL® SBC finish. Spacing between
control joints is determined by wall height. In general the ratio of
control joint spacing to wall height is about 2:1. That is a 2' high
wall should have control joints every 4', a 4' wall every 8', and an
8' wall every 16' to 20'.
Control joints
are also needed at the following points of weakness and/or high
stress concentration.
- At all abrupt
changes in wall height
- At all
changes in wall thickness, such as those at pipe or duct columns
or pilaster
- Above joints
in foundations and floors
- Below joints
in roots and floors that bear on the wall
- At a distance
of not over half the allowable joint spacing from bonded
intersections or corners
- At one or
both sides of all door and window openings unless other crack
control measures are used, i.e., joint reinforcement or bond beams
Regardless of
the control joint design used, rake out the wall joint and caulk
with QUIKRETE® Concrete Repair Caulk.



9. Attach
capping sills to the top course by anchoring bolts firmly into the
concrete or QUIKWALL® SBC. Moist-cure the wall after 8 hours by
dampening with a fine spray. Repeat several times daily for 3 days.
Roof or floor construction can proceed when the curing is
complete.

For Best
Results
- Take extra
care that the bottom course is laid properly, because each
succeeding course will simply be stacked on it.
- To ensure
proper bonding, make certain that the blocks are clean and free of
any dirt, soil, or grease.
- Before laying
the block, remove any burrs and chips from it with a hammer to get
a tight fit. Mix only as much QUIKWALL® SBC as can be used in 1
hour.
- To obtain the
finish you desire, experiment with different trowels and
techniques before applying the QUIKWALL® SBC coat to your wall.
|